The applicant lodges a private plan change request with the district or regional council.
-
The council processes the request, can request further information and commission reports if necessary.
-
The council may modify the request with the applicant's permission if appropriate.
-
The council decides whether to adopt, accept, or reject the request, or convert the request to a resource consent.
-
The council publicly notifies a request that it has adopted or accepted allowing submissions and further submissions to then be made.
-
The council holds a hearing where it assesses the request and submissions made and then issues a decision on the request.
-
The council decision can be appealed to the Environment Court.